Update to Water Notice-17th October 2019.

Update to Water Notice-17th October 2019.

Dear Jolly Harbour Property Owners/Tenants

Please be informed that CDAL (and the surrounding communities) have been receiving very little water over the past month and essential zero supply to Jolly Harbour since last Friday. As a result, the main tank is essentially empty. This is a result of production reduction at the Frye’s Beach water plant (see attached notice from APUA). Unfortunately, we have been given no timeframe as to when these problems will be rectified.
 
We are therefore asking ALL property owners/residents to switch over to your cisterns and to practice water conservation until further notice.
 
As an update on the desal plant, the plant is here and secured. The commissioning team from the U.S. is due in the last week of October. We are tentatively scheduling to be up and running by mid-November.

Kind Regards,
CDAL Management